A drawing extends the existing rafters in a straight line and shows the old and new slates meeting flush. The carpenter has been asked to board the new slope. On the old slope, the underlay lies over open rafters and the slating battens sit directly above it. Even if the two sets of rafters line up perfectly, the finished slate faces may land at different heights.
Welsh Slate illustrates both assemblies in its roofing brochure. Over a boarded roof its detail includes counterbattens running up the slope under the horizontal slating battens. This leaves space for drainage and ventilation below the slates. Copying just the horizontal batten from the open-rafter detail drops an intentional part of the boarded assembly.
Compare two stacks from the same reference line
Have the designer draw a section through each roof alongside the junction, with the tops of the rafters on the same reference line. Record the boarding, counterbattens, slating battens and slate build-up at the same point in a course. Use measured dimensions for the existing layers and the proposed sizes for the new ones. For a drawing exercise, adding 18 mm of boarding and a 25 mm counterbatten while keeping every other layer equal creates a 43 mm difference measured perpendicular to the slope. Those are example dimensions, not a recommended assembly.
Put that discrepancy in front of the designer while the new rafter levels can still be set. Ask for a section showing both the finished slate line and where water on the new underlay will drain. Record the resolved heights on the addition design brief used by the carpenter and the slater. Otherwise one trade may price a flush join while the other has allowed for a step.