A tapered addition can look like an ordinary gable in a front elevation. Seen from above, the outside wall may step progressively farther from the same line of tile joints as you move uphill. That difference matters when the schedule calls for a molded edge tile with a downturned side that finishes the verge.
Marley’s UK page for its concrete interlocking cloak verge lists compatible profiles and a permitted range of batten spacings. It also excludes raking verges. Selecting a supported field tile and a spacing within the published range answers only part of the question. The edge still has to run in a direction the fitting can follow.
Mark the edge on the roof plan
Draw a line up the roof perpendicular to the eave and compare it with the gable edge. If they diverge, show the sideways offset at the bottom and top of the run. On a remodel, check those positions against the existing wall. A dimension along the sloping edge alone gives its length but loses the direction of the cut across successive courses.
Send the marked plan, field tile identification and proposed edge section to the designer and tile supplier before releasing the fittings. Ask them to identify the supported termination for that edge. Keep the straight verge and the oblique verge as separate order lines until the details are settled. The gable trim bid comparison can then assign quantities to the detail that each bidder actually priced.