A replacement gutter can collect water from the whole bottom row of concrete tiles and still miss water from the gable. Some continuous verge trims have a narrow drainage channel running down the sloping edge. At the eave, that little channel has its own discharge point. Its position sideways along the fascia matters just as much as how far the field tiles project over the gutter.
Kytun’s standard tile dry verge guide tells the installer to position the gutter to receive the trim channel. Imagine two contractors working from different drawings. One finishes the gutter with a stop end flush with the gable wall. The other sets out the verge against the bargeboard farther out. Both pieces can look straight and tidy while the outlet falls beyond the stop end.
Draw the corner looking down
Ask for a small plan view showing the channel outlet, the open top of the gutter and the inside face of its stop end. On the same sketch, show the fascia and bargeboard so everyone is measuring from the same edges. A section cut halfway along the eave can confirm the tile overhang while missing the sideways offset entirely.
On a gutter-only job, have the installer locate the existing outlet before cutting the new length. On a reroof, agree who sets the stop end and who checks the finished channel against it. If the job instead calls for individual caps on each course, identify the actual model and its drainage detail before using this sketch. The Guild’s guide to interlocking verge units covers the course spacing those products need.