A condominium board receives a lift-and-relay proposal for one building. Its reserve schedule already has lines for “tile roof replacement” and “underlayment.” Adding the full proposal to both could count the same work twice. Deleting the tile line entirely could leave the other buildings without an allowance. The first step is to find out what each existing line buys.
The Community Associations Institute’s Reserve Study Standards call for a component inventory that identifies quantities or descriptions, sources, useful and remaining life, and current replacement cost. Ask the reserve professional for the assumptions behind each roof entry. A date beside “tile roof” gives the board little basis for a change if nobody can say which buildings or layers the entry includes.
Trace one building through the estimate
Suppose the association owns two similar buildings, East and West. The contractor’s proposal covers East only. On a copy of the estimate, mark where it prices access, lifting and storing existing concrete tiles, replacing the underlayment, buying compatible replacements for broken pieces and relaying the covering. Beside each task, identify the reserve line, building and quantity that currently include it. Put a question mark against any line whose scope is unknown. Count shared mobilisation once for the proposed East job; do not assume it will also cover a future visit to West.
After the job, give the reserve professional the invoice, actual area completed, dates and any exclusions. If the crew retained the original field tiles, record that fact separately from the new underlayment installation date. It helps the next board understand why two components on the same slope have different histories. Keep the association’s warranty records with the closeout documents. Ask the reserve professional to reconcile the affected entries and leave West’s forecast tied to evidence from West.