A turret framed against a wall can look like the architect’s half-cone in elevation even when the built roof sweeps through a slightly different angle in plan. That difference matters to the factory making a set of tapered tiles. A count of how many tiles fit around the base does not tell the factory how far those courses must run up the slope.
Detail MC-28A in the Tile Roofing Industry Alliance manual asks the contractor to check the completed framing against the drawings for two dimensions: the distance along the slope and the angle of the sector. It places this check before the underlayment goes down. In plan the sector angle describes how much of the circle the roof occupies. In section the slope distance runs along the cone. The vertical rise or the roof pitch alone cannot supply both pieces of information.
Put the field dimensions on the factory sheet
Have the fabricator mark the endpoints it used for the slope measurement and the two radial boundaries it used in plan. Ask the framing and roofing teams to return the same sheet with the corresponding field dimensions, date and location. For a partial cone, identify the wall or return at each end. A photograph of the curved eave is useful context but cannot substitute for those dimensions.
If the field sheet disagrees with the factory drawing, identify who will resolve the framing or revise the tile set before releasing it. Keep the approved revision with the delivery paperwork. The Guild’s guide to identifying tower tiles by course explains how to keep the resulting pieces in order once they arrive.