The contractor can reach the copper gutter from the scaffold. The room below the slate eave is behind a locked door. If the metalwork proposal involves soldering, the person who holds that key belongs in the planning conversation before the workday is booked.
Historic England advises avoiding hot work at historic buildings whenever possible. Ask the sheet-metal designer which joints can be made in the workshop and which can be detailed without on-site heat. If there is genuinely no alternative, the guidance calls for a permit covering the particular operation, location and time. Its guidance calls for monitoring the work area for at least an hour after work ends and a return inspection two hours after completion, including adjoining spaces where heat or sparks could have travelled.
Put the last inspection on the programme
Have the responsible person and contractor mark the joint on an elevation and locate the roof void or room directly behind it on a floor plan. Establish who can enter those spaces, when they will be occupied and who will be available for the agreed monitoring and later inspection. Historic England’s example for lead roof repairs sets a stop time for hot work at least two hours ahead of site closure. Use the monitoring requirements adopted for this project to work backward from its closing time.
A delay matters. If access to the room ends before the checks will be complete, reschedule the operation with the responsible person. Include the internal access arrangement alongside the shop and field seam record so a postponed joint does not migrate to a different day under the old permit.