A house can have a working underground electric supply and still have its old service attachment on the roof. When the mast passes through slate, the owner has two closeout questions: who removes the obsolete equipment, and who makes the roof weathertight on the day it comes out?
DTE Energy describes an underground conversion in two stages. An underground crew installs the cable. An overhead crew removes the overhead lines and makes the connection at the pole. The utility assigns removal of the former attachment and service-entrance equipment on the house to the customer or contractor. That distinction matters when an estimate simply says “remove overhead service.”
Put one handoff on both work orders
Ask the electrician to identify the equipment being retired and coordinate its release with the serving utility. Give the roofer a photograph and the location of the penetration on the slope, plus a view from below if one is already available. Request separate prices for lifting adjacent courses, repairing the opening in the substrate and reinstating matching slates. Identify who will provide temporary weather protection if the deck condition prevents a permanent repair that day.
Before the roofer mobilizes, confirm that the electrical parties have released the work area. A missing wire in a photograph cannot establish that. When comparing the roof repair estimates, check that both cover the same opening, including any support attachments being removed. The utility completion notice and a photograph of the finished slate patch belong to different work orders.