Does a slate declaration prove a tighter carbonate limit?

Read the inequality on a roofing slate declaration before accepting or rejecting a bid against a project-specific carbonate limit.

By the Slate, Tile & Metal Guild ·

A tender reviewer sees 5% on a slate declaration and 3% in a project schedule. Marking the bid as a failure would be premature. Read the sign immediately before the number and the name of the property immediately above it.

Welsh Slate’s January 2025 declaration for Cwt-y-Bugail Celtic gives an upper bound of 5% for apparent calcium carbonate. Farther down the page it declares compliance with a 2% upper bound for non-carbonate carbon. Both figures are percentages. They answer different questions about the stone. Only the first addresses a requirement written for apparent calcium carbonate.

Try the comparison both ways

Suppose a tender requires apparent calcium carbonate of 5% or less and allows a manufacturer’s declaration as evidence. For the named product, the declared upper bound answers that particular line. Now suppose the project sets a maximum of 3%. An actual value of 2.5% and one of 4% would both fit the declaration. Only the first would fit the tighter requirement. Neither is a measured result for this product. The declaration alone leaves that tender question open.

Keep the inequality in the comparison sheet. A spreadsheet entry of “5” turns a ceiling into an apparent measurement. Copying the smaller 2% figure from the carbon row would produce an apparent pass for the wrong property. A single cell for “carbon” leaves the next reviewer unable to tell which mistake occurred.

Ask for the missing evidence

Give the supplier the exact clause, proposed quarry and grade, and declaration reference. Ask whether they can document the specified property to the tighter limit on the basis the tender requires. If they supply a measured sample result, identify the sample and ask the specifier whether that evidence represents the material being offered. Keep the disposition with the bid so an unresolved question does not become an approved substitution when the order is written.

For another easily misplaced declaration entry, see the Guild’s guide to the two uses of S1 in slate specifications.

Further reading

Welsh Slate · Cwt-y-Bugail Celtic declaration of performance, January 2025. The two percentages quoted here belong to document BPWS 107, version 5. The tighter tender limit in the worked example is hypothetical.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.