A tilt indicator is red on a slate crate. What belongs on the delivery receipt?

Record the indicator separately from any confirmed slate breakage and keep the affected crate traceable through inspection.

By the Slate, Tile & Metal Guild ·

A shipment arrives with three crates of the same size roofing slate. Two look undisturbed. The third carries a tilt indicator with a red window, but no broken pieces are visible from the outside. The person signing the receipt needs to describe what can be seen before that crate is moved or mixed with the others.

Connect the observation to one crate

Read the actual indicator label. SpotSee’s companion label for the TiltWatch XTR calls for a receipt notation and an inspection when the indicator shows red. Photograph the indicator and crate identifier together, then take a wider view showing its position in the shipment. Write a plain observation such as “Crate C, red tilt indicator on arrival, contents awaiting inspection.” Note any visible damage separately. The indicator alone cannot tell the supplier which slates broke, how many are usable, or at what point in transit the tilt occurred.

Keep the inspection tied to the delivery

Ask the receiving lead to follow the shipper’s instructions and the procedure for that carrier before releasing the crate into general stock. If inspection finds damage, SpotSee directs the receiver to preserve the original packaging and request carrier inspection within the applicable period. An unstable load needs the site’s qualified material handler before anyone approaches it to open or count it.

When the crate can be inspected, record the size, finish and count actually examined. If only the upper row has been checked, say so. A partial count provides a reason to inspect further, but it cannot supply a breakage percentage for the entire order. Send the supplier the receipt notation, crate photos and confirmed piece count together. That lets the purchaser request the right replacement stock while keeping unexamined pieces out of the shortage calculation.

The Guild’s delivery drop-point guide helps the receiving lead identify where inspection can take place before a shipment arrives.

Further reading

SpotSee — TiltWatch XTR mounting instructions and companion receiving label. The manufacturer’s instructions apply to the named indicator. The slate receiving example is hypothetical.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles