A porch needs a new membrane. Its upper edge disappears beneath the slates on the house, and one estimate includes removing just the lowest visible course. Before comparing that price with a larger strip-back allowance, ask the bidders where they expect the new membrane to end and where the reinstated slates can be nailed.
The National Slate Association’s detail for a low-slope roof below slate carries the membrane uphill under the slates. The distance depends in part on what may accumulate at the junction, including snow sliding off the upper slope. The guide calls for slating nails to avoid puncturing that membrane. The membrane manufacturer also has requirements for securing and finishing its upper edge.
Put the termination and the nails on one section
On a section through the junction, have the designer mark the proposed top of the membrane. Ask the slater to draw in the existing courses at their measured exposures and identify the fixing positions needed to put them back. The distance from the porch to the first visible slate joint gives only the exposed course height. It reveals neither the membrane edge nor the location of the concealed nails.
If the existing junction has never been opened, the estimate can identify the assumed strip-back and a unit for additional work if the termination proves higher. Agree who records the actual edge in the first opening and who reviews a conflict before the slates go back. For the wider division of responsibility, see Slate Roofing USA’s guide to slate and low-slope junctions.