On one sheet of a slate reroof drawing set, the field underlayment crosses the valley from both slopes. On another, its edge is shown lying over the metal lining. Both drawings may look familiar to a slater. They describe different ways to assemble the concealed layers.
The National Slate Association field guide illustrates a woven arrangement in which successive field sheets cross the valley and are covered by sheets from the other side. The valley metal then sits above the weave. In its overlapping detail for an open valley, a strip first runs along the valley, the metal follows, and the field sheets lap onto the metal edges. The association advises against that overlapping arrangement for closed valleys.
Read the stack from deck to slate
Ask the designer for a section taken across the valley where the slates have been left off the drawing. Starting at the deck, number each sheet in the order it goes down. Draw the outer edge of the metal as well as the visible edges of the finished channel. If an instruction asks for the same sheet to cross underneath the metal and also lap over its edge, flag the conflict while both sheets are still on the desk.
Once the designer confirms the intended assembly, agree when the installer should photograph it. A picture after slating may show the finished channel width clearly and still leave the concealed laps entirely out of view.