Preserving the craft. Building its future.

Clay tile · Trim takeoff

Where does a dormer add end-band tile to a Spanish S-tile order?

Follow each interruption in a Spanish S-tile field to locate the end-band fittings and their concealed wood supports.

By the Slate, Tile & Metal Guild ·

A trim estimate shows both gable rakes and every foot of ridge. Now draw a dormer in the middle of that roof. The outside perimeter stays the same, but the field tiles now stop and start against the dormer cheeks. One of those interruptions can add a run of clay fittings and a strip of concealed carpentry.

Ludowici’s Spanish S-tile instructions call for an end band where the left side of a field terminates, including at a dormer, chimney or parapet. Its gable detail shows two separate clay pieces, the end band and the detached rake. A wood nailer supports the end band and gives its fasteners somewhere to land. An allowance for gable trim alone can miss both the inner interruption and its nailer.

Trace the edge of the tile field

On the elevation, shade the roof area that actually receives field tile. At the dormer, mark the left-hand boundary of each adjoining patch of tile using the maker’s orientation. A note that says “left cheek of dormer” is ambiguous until the drawing shows which field the note describes. For the orientation of the gable fittings, see the Guild’s guide to ordering handed rake tile.

Have the installer mark where each band starts and stops, tally the affected courses and identify the support on the corresponding section. Ask the supplier to return the fitting count against those marks. Keep the wall flashing on its own detail and order line. If the roof plan changes from one dormer to two, that marked elevation shows which quantities need another look before the shop releases the order.

Further reading

Ludowici — Barrel Tile Installation Manual, Spanish end-band nailer and Figure 36.1, p. 36. The detail applies to the maker’s Spanish S-tile system. Check the selected profile and project details.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles