How do you move stored slate onto a progress bill without counting it twice?

Follow a crate of roofing slate from storage to installation and reconcile its material value across two payment applications.

By the Slate, Tile & Metal Guild ·

A school has already approved the material value of four crates of roofing slate stored on site. By the next billing date the slaters have installed three crates on the library wing. The foreman’s installation count is right. The supplier’s original delivery ticket is right. Adding both figures together would still overstate the work.

Follow the same four crates across two dates

Suppose the material value accepted for each crate was $2,000. At the first cutoff, the application carried $8,000 in storage and zero installed for that lot. At the second cutoff, assuming three complete crates went into the roof, the split is $6,000 installed and $2,000 still stored. Total material value accounted for remains $8,000. If the second application shows $6,000 installed and the old $8,000 balance in storage, it claims $14,000 against the same four crates.

The sample AIA G703–1992 continuation sheet makes the distinction visible. Column F asks what is presently stored, excluding the work reported in D and E. G brings those amounts together. Read F as a balance at the cutoff. Treating it as a running sum of all deliveries leaves the first month’s crates on the books after installation.

What if the fourth crate is open?

Keep its identifier on the count sheet. Record which sizes remain and match them to the material breakdown used in the application. A half-empty crate of large slates need not carry half the value of a mixed delivery. If pieces broke or moved to a different wing, give those pieces their own entry and reconcile their treatment before rolling the figure forward. The Guild’s part-crate storage guide explains how to keep the remaining slate identifiable.

This example isolates material to show the transfer. Installation labor earned in the period belongs in the applicable work item, and retainage belongs in the separate calculation required by the project. For a real review, first check the signed payment terms for eligibility and supporting records. A delivery ticket locates a shipment in time. The dated balance and installation record explain what the current request actually covers.

Further reading

AIA Contract Documents · G703–1992 sample continuation sheet. The cited edition distinguishes completed work from materials presently stored. Figures in the example are hypothetical and cover material value only.

Published by the Guild as part of Tim Kelly’s Slate Boss resource network. These educational guides support project conversations and do not replace an on-site inspection or a project specification.

← All roofing articles