A uniform slate roof is going on in two phases. One slope starts Monday. Scaffolding for the other will arrive a fortnight later. Both slopes draw from the same delivery. If the first crew simply picks the thickest stones whenever it needs another piece, what will be left when the second crew starts at its eave?
The National Slate Association’s guide specification calls for sorting by thickness before installation. It assigns the thickest group near the eave, an intermediate group farther up the slope and the thinnest near the ridge. It also calls for blending colour from different pallets. These tasks can be done together. A pile chosen solely by pallet colour can still contain stones of several thicknesses.
Allocate both starts while the stock is visible
Suppose the slater’s course schedule assigns 60 full field pieces from the thicker group to the lower part of each slope. The yard has sorted 128 suitable pieces. Mark 60 for the first slope, 60 for the second and eight available to resolve cuts or breakage. If the first crew takes 75, only 53 remain for a scheduled group of 60. Counting all the medium and thin pieces still in stock could hide that shortfall.
Have the slater check each allocation for colour distribution in daylight. Tag the staging areas by slope and thickness group. Show any specials on their own lines and revise the count when the course schedule changes. Keep the allocation with the approved colour sample record so a later crew can reproduce both the blend and the build-up the first crew started.