A slate-clad gable has two sets of lines to resolve. The wall slates advance in horizontal courses. The underside of the projecting roof edge, known as the verge, rises diagonally across them. The end piece in each course must reconcile those lines, and it may bear little resemblance to a full rectangular field slate.
SSQ’s fixing guide illustrates two ways to finish this run. In one, the slater cuts a wider piece to fit beneath the verge, leaving the clearance shown in the detail. In the other, the cut is shared between the last two pieces in the course so that the lower edge of the end piece meets the verge at nearly a right angle. Look at the line of those lower edges on the elevation. The two finishes will read differently from the street.
Detail several course ends together
For a replacement to match surviving work, ask for a straight-on photograph showing several intact courses at the rake. Trace the visible joints at the ends. For new work, have the designer draw the same few courses to scale with the actual slate width and the roof pitch. Mark which pieces need extra width and which can come from field stock. A single typical slate drawn in isolation cannot show how the joints in successive courses will fall.
Use the approved elevation to prepare a separate list of end pieces before the supplier packs the order. Keep that list with the vertical-slate area takeoff. One establishes which widths must be available for the cuts; the other records the surface being covered.