A survey for slate repairs identifies a narrow vertical enclosure from the clock room down through the tower. It looks like a tidy place to route the lead for temporary lighting, well away from the scaffold stairs. Before it appears on the access drawing, ask the clock keeper what travels through that space.
Some mechanical turret clocks are weight driven. The enclosure may be the path of a suspended weight, and a view through one opening shows only part of its travel. The Church Buildings Council’s clock guidance specifically excludes using a weight chute for electrical runs or storage and says people must be kept out of the space beneath the weights. An apparently empty section at the hour of a survey is no basis for allocating it to the roofing crew.
Mark the space in section
Give the clock specialist a section through the levels the crew expects to use. Have the specialist identify the chute, its lowest extent and the access needed to service the clock. Ask the site supervisor to mark a separate cable run and check where people will stand when passing slates or handling equipment. A floor plan can show routes that seem separate while placing a person directly beneath a moving load on the floor above.
Put the agreed route at the tower entrance with the working drawings. If an access hatch cannot be identified during the survey, leave it out of the proposed route until the custodian resolves it. If work affects the clock or striking gear, arrange the decision and any shutdown with the responsible specialists. The exterior debris route belongs on the site plan as well, so a last-minute change outside does not divert materials into the tower.