A church asks two firms to price a slate reroof. Both allow for scaffold and a debris chute. One assumes the parish will protect the windows, and the other allows for a screen only while slates are being stripped. The first scaffold tube will pass the west window before either arrangement takes effect. Who has priced protection for that moment, and for the day the scaffold comes down?
Put the windows on the roofing drawing
Give each affected window a short identifier. Include the one beside the route for carrying tubes as well as the one directly beneath the eaves. Photograph each from an agreed viewpoint with the custodian. Mark the loading bay and the route for removed slates on the same elevation. Moving the loading bay may solve a problem that would otherwise need a substantial enclosure.
Invite the glazing conservator and scaffold designer to review the drawing together. Ask what the screen must withstand, what can support it clear of the glass, and how the conservator will inspect the window while it is covered. A dust sheet and an impact screen serve different purposes. Historic England also flags a less obvious risk with tightly enclosed features. Restricted air movement can allow moisture to accumulate behind the protection.
Price installation and removal
For each window, record who provides the protection, which operation first puts the glass at risk and which operation ends that risk. Agree a way to check the glass if the screen shifts. When the scaffold team changes its dismantling sequence, revisit the removal date with the custodian. Keep the before and after photographs under the same window identifier so the next inspection starts with a comparable view.