A phased slate roof can leave months between the first material quotation and the release of a second slope. A proposal that promises to “adjust for inflation” leaves two numbers open: the measure of price change and the amount to which it applies. Ask the bidder to demonstrate the calculation while the original quotation is still on the table.
Run a sample invoice
Suppose the later phase includes $20,000 for roofing slate, $2,000 for freight and $8,000 for installation. In this example the agreement adjusts only the slate supply. If the selected index moves from 200 to 210, the change is 210 divided by 200, minus one, or 5 percent. The material adjustment is $1,000. The revised total is $31,000. Applying that percentage to the whole $30,000 would add $500 more by escalating two fixed lines.
The U.S. Bureau of Labor Statistics recommends identifying the base price, its month and year, and the index series used. Ask for the series title and identifier, the comparison month and the version of the published value the parties will use if figures are revised. An index measures change. Its numerical level supplies no price per roofing square.
Mark quantities that have already been released at a fixed price. If the second phase changes slate size or thickness, have the supplier identify the price change attributable to the revised product before applying the agreed timing adjustment. Keep the example with the record of material already stored and billed. That makes a later invoice reproducible from the original figures.