The slate contractor’s tender includes scaffold at the street elevation. A separate drawing shows that elevation screened while the old slates come off. Both bidders have measured the same frontage, yet they may have priced different structures. Start with the scaffold quotation and check whether the designer was told about the screen.
Britain’s Health and Safety Executive instructs users to inform the people responsible for scaffold design and erection before adding sheeting or debris netting. They need to check that the scaffold is designed for the addition. Treat a request to screen an open scaffold as a design question even if the screen is only needed during stripping.
Describe the screen the contractor priced
Mark the proposed screening on an elevation. Include its upper and lower limits, whether it continues around a corner, the proposed material, and the stages of work during which it will be in place. Send those details to the scaffold provider. A quote that says “netting by roofer” assigns a supply task. It leaves open whether the design already allows for that netting and who must approve a later change.
For example, a building owner might want the lower level screened throughout a project and the upper level screened only while slates are removed. Ask the scaffold provider to identify the arrangements covered by its design and quotation, and get any revised design or cost back before comparing bids. Retain the answer with the marked elevation so that a change during construction goes back to the right person.
Plan the movement of removed slates separately. A screen does not tell the site manager how heavy pieces will reach the container or how the area below will be controlled. The Guild’s guide to the tear-off debris route addresses that decision.